You are here:Home / News / Project Update: Clean Fuel & Sulphur Recovery Unit Project

Project Update: Clean Fuel & Sulphur Recovery Unit Project

The construction works are progressing smoothly and the civil works activities have reached 23% of completion
 Project Update:  Clean Fuel & Sulphur Recovery Unit Project

The Mechanical sub-contractor has been mobilized and the structural steel erection activities have started with the Pipe Rack erection in the Clean Fuel Area. All construction activities have been performed without any Lost Time Injury case (LTI = 0) and without any Total Recordable Incident (TRI=0), demonstrating KT/TAL’s world-class Health & Safety performance with regard to the execution of activities.

This important target, achieved in close cooperation with the Client Petro Rabigh, was made possible by the application of the HSE Management System and the effort to involve the Subcontractors in the development and application of the Safety-First concept.